7. Technical and Regulatory Challenges and Solutions

Although BCRs can remove metals or other constituents of concern from MIW, in many instances their performance has not been perceived as consistently repeatable from site to site. This perceived lack of consistency can be overcome through careful planning, engineering, and design. Proper attention must therefore be paid to the site-specific technical aspects of a project and regulatory requirements to determine the potential applicability of BCRs.

7.1 Technical Challenges

MIW is generally a result of uncontrolled releases of constituents of concern from historical operations over large or remote areas. Because of changes in regulations, releases from new mines are not as common or extensive as releases from historical mining operations. Table 7-1 presents some of the typical technical issues that can be encountered and references to specific sections within this document that address these issues.

7.2 Legislative and Regulatory Challenges

Often, there are many permitting issues that must be addressed when constructing treatment systems, from land disturbance and erosion and stormwater control issues to discharge permits for active mining operations. BCRs have applicability across the country at abandoned and active mining sites; however, local, tribal, and state and federal regulations may differ for each site. Federal requirements are discussed on the National Pollutant Discharge Elimination System (NPDES) web site mining page (USEPA 2012). All required permitting agencies should be consulted throughout the process to ensure that appropriate regulatory processes are being followed. Note that the following discussion does not include all of the existing regulatory programs in every state.

Most of the early BCRs were used on abandoned or inactive sites. In these cases, the receiving streams were often devoid of aquatic life. The goal of treatment was to improve water quality in the stream so that it could once again support an aquatic community. As a result, the key issue was usually increasing the pH and reducing the metal toxicity of the discharge. No strict numeric standards were imposed. A well-designed passive treatment system will increase pH and remove metals, but may not be able to continually meet strict numeric limits. Pennsylvania still allows passive systems, including BCRs, to be used at abandoned sites without permit restrictions. These are considered to be more like a best management practice, rather than a permitted facility. The West Fork BCR system (see Appendix B.7) in Missouri is operated under an NPDES permit. Regulatory challenges at this site are discussed in Gusek et al. (1998)

As the technology has matured, there are a growing number of applications where the goal is to meet NPDES discharge standards. Although BCRs can generally meet pH limits, meeting very low chronic toxicity standards can be problematic. However, the biotic ligandA chemical which interacts with a metal to bind that metal into a complex. model, which accounts for reductions in toxicity when metals are complexed with organic carbon typically found in BCR effluent, may be worth examination in the context of BCR permitting.  In addition, the initial water from the BCR can contain high levels of organic carbon and nutrients. These parameters may require some form of management or treatment prior to discharges as described in Section 2.5 and Section 4.3.5.

7.3 Disposition of Residual Materials

As with all residual materials, the designation of waste must consider if the material still has economic value. In many cases residual materials from BCRs can include high concentrations of metals that may prove to be economically recoverable (Gusek and Clarke-Whistler 2005; Gusek, Wildeman, and Conroy 2006). Use care in appropriately evaluating and managing any residual material removed from a BCR. In the federal code, 40 CFRCode of Federal Regulations 261.24 lists the maximum concentration of contaminants for the characteristic of toxicity from the toxicity characteristic leaching procedure (TCLP) test that would define a substrate as hazardous waste or not. Nevertheless an in-depth review of all materials removed from the system routinely or at the end of its service life should be done to establish proper disposition (see Section 2.5.3 and Section 6.3.1).

7.4 Wetlands (CTW and Mitigation)

One of the most pressing challenges in some areas is how to address wetlands present at a site. Differences exist between United States Army Corp of Engineers (USACE) districts as to the applicability of §404 of the Clean Water Act (CWA) to wetlands that were created by mine drainage. In order to create treatment systems for MIW, occasionally, poor quality wetlands created by the MIW must be removed. Consult with the local USACE district and other agencies at the planning stage to determine regulatory requirements regarding any wetlands that may be present and any mitigation (in-kind, out-of-kind, on-site, or off-site) that may need to be performed. Additionally, tribal, state, and local agencies should also be consulted about wetland permitting and mitigation issues. For additional guidance, see Chapters 7 and 8 of ITRC's WLTD-2 document (ITRC 2005).

Mayer Ranch Wetlands Mitigation

At the Mayer Ranch Superfund site, mitigation of the volunteer cattail wetlands that sprung up after the mine water began to discharge in 1979 was not required. In theory, the clean polishing pond at the end of the treatment system could replace (in terms of mitigation credits) the contaminated volunteer wetlands that were destroyed during construction of the treatment system.

 

 

 

 

 

 

Publication Date: November 2013

Permission is granted to refer to or quote from this publication with the customary acknowledgment of the source (see suggested citation and disclaimer).

 

This web site is owned by ITRC.

1250 H Street, NW • Suite 850 • Washington, DC 20005

(202) 266-4933 • Email: [email protected]

Terms of Service, Privacy Policy, and Usage Policy

 

ITRC is sponsored by the Environmental Council of the States.